ocds-j74acu-017577-AN/WRK/01
ADDITIONAL WORKS INCLUDING CEMENT SAND STABILIZATION FOR THE COMPLETION OF AMANSEA-NDIUKWUENU-MANU FOREST-AWA-UFUMA ROAD PROJECT
Planning |
|
|---|---|
| OCID: | ocds-j74acu-017577-AN/WRK/01 |
| Project Title: | ADDITIONAL WORKS INCLUDING CEMENT SAND STABILIZATION FOR THE COMPLETION OF AMANSEA-NDIUKWUENU-MANU FOREST-AWA-UFUMA ROAD PROJECT |
| Procuring Entity: | MINISTRY OF WORKS & INFRASTRUCTURE |
| Planning Rationale: | selective |
| Budget ID: | 017576 |
| Budget Description: | ADDITIONAL WORKS INCLUDING CEMENT SAND STABILIZATION FOR THE COMPLETION OF AMANSEA-NDIUKWUENU-MANU FOREST-AWA-UFUMA ROAD PROJECT WITH A GUARANTEE OF THIRTY (30) YEARS |
| Budget Amount: | ₦6,539,304,639.21 |
| Budget Year: | 2022 |
| Procurement Method: | selective |
| Procurement Category: | works |
| S/N | Company | Envelope | Bid Opening Status | Tender Amount | Financial Bid Score % | E.O Award Status |
|---|---|---|---|---|---|---|
| 1 | Messrs Steffanutti Stock Hapel Nig. Ltd | Price BOQ | Opened | 6,470,000,000.00 | -99.999999907264 | Awarded |
AWARD |
|
|---|---|
| Award Title: | ADDITIONAL WORKS INCLUDING CEMENT SAND STABILIZATION FOR THE COMPLETION OF AMANSEA-NDIUKWUENU-MANU FOREST-AWA-UFUMA ROAD PROJECT |
| Award Description : | ADDITIONAL WORKS INCLUDING CEMENT SAND STABILIZATION FOR THE COMPLETION OF AMANSEA-NDIUKWUENU-MANU FOREST-AWA-UFUMA ROAD PROJECT WITH A GUARANTEE OF THIRTY (30) YEARS |
| Award ID : | ocds-j74acu-017577-AN/WRK/01i/ocds-j74acu-017577-AN/WRK/01017594 |
| Award Status : | active |
| Award Date: | 2013-04-05T08:36 |
| Award Criteria : | price Only |
| Award Amount : | ₦6,470,000,000 |
| Award Items Classification Scheme : | |
| Award Items Classification ID : | 100 |
| Award Items Quantity: | 1 |
| Award Items Unit : | Lot |
| Award Items Delivery Address : | Anambra State |
| Contract Period Start Date : | 2013-04-19T13:55 |
| Contract Period End Date : | 20223-02-11T19:10 |
| Contract Period Duration in Days : | -15815 |
| Contractor/Supplier Name : | Messrs Steffanutti Stock Hapel Nig. Ltd |
| Contractor/Supplier Address : | PLOT 14/15 OLD AIRPORT ROAD EMENE , ENUGU , ENUGU |
| Contractor/Supplier Email : | |
| Contractor/Supplier Phone : | |
| Contractor/Supplier website : | https://www.eprocure.bpp.an.gov.ng/report/economic_operator.php |
| Procuring Entity Name: | MINISTRY OF WORKS & INFRASTRUCTURE |
| Procuring Entity Address : | Ministry of Works, Amawbia, Awka |
| Procuring Entity Representative Email.: | works@eprocure.bpp.an.gov.ng |
| Procuring Entity Representative Phone : | 07036702741 |
| Procuring Entity website : | https://anambrastate.gov.ng/ |
Contract |
|
|---|---|
| Contract Title : | ADDITIONAL WORKS INCLUDING CEMENT SAND STABILIZATION FOR THE COMPLETION OF AMANSEA-NDIUKWUENU-MANU FOREST-AWA-UFUMA ROAD PROJECT |
| Contract Description: | ADDITIONAL WORKS INCLUDING CEMENT SAND STABILIZATION FOR THE COMPLETION OF AMANSEA-NDIUKWUENU-MANU FOREST-AWA-UFUMA ROAD PROJECT WITH A GUARANTEE OF THIRTY (30) YEARS |
| Contract Award ID : | ocds-j74acu-017577-AN/WRK/01 |
| Contract Status : | active |
| Contract Period Start Date : | 2013-04-19T13:55 |
| Contract Period End Date : | 20223-02-11T19:10 |
| Contract Period Duration in Days : | -15815 |
| Contract Amount : | 6470000000 |
| Contract Date Signed : | 2013-04-18T08:36 |
| Contract Item Classification Scheme : | UNSPSC |
| Contract Item Classification ID : | 100 |
| Contract Item Quantity : | 1 |
| Contract Item Unit : | Lot |
| Contract Item Delivery Address : | Anambra State |
Implementation |
|
|---|---|
| Contract Implementation ID: | ocds-j74acu-017577-AN/WRK/01017674 |
| Payer Name : | MINISTRY OF WORKS & INFRASTRUCTURE |
| Payee Name: | Messrs Steffanutti Stock Hapel Nig. Ltd |
| Contract Period Start Date : | 2013-04-19T13:55 |
| Contract Period End Date: | 20223-02-11T19:10 |
| Contract Period Duration in Days : | -15815 |
| Amount Paid : | 6470000000 |
| Balance to be paid : | 6469999994 |
| Implementation Status: | Ongoing |